S&S took on the challenge of pouring concrete with power float finish to an 8 storey apartment block which will be 250 apartments.
Completing within the scheduled time frame, this was especially difficult due to the amount of columns and steel work that ran all the way through each floor.
This job at Warrington was a total of 28,000m2 of concrete that was laid.
Steel Mill - Sunderland
1000m2 of concrete per bay each with a water channel in-between, 4 bays in total.
Full polish finish on each of the slab.
S&S completed the setting up of mesh and laid the concrete as wet screed. Achieving tolerances of +/- 5mm from datum
Pig Shed - Helmsley
This job consisted of 2000m2 of concrete with power float finish. The slab needed to be laid first so that the frame work could be built up off the ground.
Markham Vale
Here we have two distribution units in Markam Vale. You can see the external yard slab has been laid with brush finish to the highest standards.
Size of the job is 20,000m2
Others
Here are few other projects by S&S Concrete Flooring.